Ten steps, the same every time

Applying the sealant is the last and the quickest part of the job. Everything that happens before it decides whether the joint lasts two years or ten. That is why we always do it in the same order.

  • Since 1959

    Experience and craftsmanship from Utrecht

  • Clear communication

    Short lines, clear agreements

  • 100% satisfaction

    We only leave once you are satisfied

  • Lasting quality

    Top-quality materials for a long-lasting result

The process

From inspection to handover

  1. Inspection

    We look at what is there and what condition it is in. Has the joint let go along the flank, or is there a tear down the middle? Those are two different problems with two different causes.

  2. Advice

    Sometimes replacing it is not necessary. Then we say so. Sometimes the problem is not the sealant but the substrate, and then new sealant is pointless until that has been sorted out.

  3. Assessing the substrate

    Will it hold? Is it dry? Is the joint wide enough? Elastic sealant needs at least 8 millimetres of width. We do not seal anything narrower, because then it tears at the first movement.

  4. Removing the old sealant

    Completely, not over the top. New sealant does not bond to old sealant. In buildings from before 1994 we first check whether there could be asbestos in it. If so we cut nothing out and report it.

  5. Cleaning and degreasing

    Dust, soap residue, silicone oil and grease are the most common cause of sealant letting go. This is dull work, and that is exactly why it often gets skipped.

  6. Fitting backing rod

    Closed-cell PE profile outside and anywhere water gets to it, open-cell PU only indoors and dry. That way the sealant bonds on two sides instead of three. If it also bonds to the bottom, the middle cannot stretch and the joint tears.

  7. Primer where needed

    Not everywhere, but where the manufacturer specifies it or where the substrate is porous. Skipping a primer saves ten minutes and costs you the whole joint.

  8. Applying the sealant

    With the type of sealant that suits the application, at the right thickness. The depth is the width divided by three, plus six millimetres. The middle thinner than the flanks, otherwise there is no give in it.

  9. Tooling and finishing

    Pulled off tight in one movement. This is where you see straight away whether someone knows the trade or not.

  10. Final check and handover

    We go over it, clear up and hand over. On commercial jobs you get a video report. On jobs for homeowners, a short set of instructions: how long not to use it, and what to keep away from it when cleaning.

Why step 6 cannot be left out

Two cross-sections side by side of the same joint recess. On the left, with a tick: the sealant is bonded to the two flanks and there is backing rod underneath, so the bottom stays free. On the right, with a cross: the sealant fills the whole recess and is bonded to the bottom as well; a tear runs down the middle of the joint.

  1. Right. With backing rod the sealant bonds to the two flanks only. The middle can stretch when the building element moves.
  2. Wrong. Without backing rod the sealant bonds to the bottom as well. At the first movement the middle has nowhere to go and the joint tears open.

Afterwards

Curing and maintenance

Curing takes longer than you think

Sealant cures at roughly two to three millimetres a day, at twenty degrees and normal humidity. So a sanitary joint six millimetres deep is only properly hard after two days. Showering earlier means water in a joint that has not closed yet.

No chlorine

Chlorine-based and abrasive cleaners wash the fungicide out of the sealant and leave the edge porous. After that mould comes back faster than it did before. A mild cleaner and a dry cloth do more than an aggressive spray.

Inspect in winter

External joints are best looked at in the cold season. The building elements have contracted then and the joint is at its widest. That is how you spot loss of adhesion that looks fine in summer.

Our advice for external work: a first check within a year of handover, and every two years after that. That is what the trade works to for facade elements as well. You get a 2-year guarantee on the work carried out; maintenance is what gives the joint its extra years after that.

Stevig Kitwerk.Watertight results.

Chat with Kitty, or message us on WhatsAppClose

Kitty

AI assistant of Stevig Kitwerk

Kitty, the mascot of Stevig Kitwerk: a white robot with a green cape and a sealant gun

Kitty

Kitty chats in Dutch. Prefer English? Use WhatsApp or e-mail below.

The conversation with Kitty only works with JavaScript on. Choose WhatsApp or e-mail below and we will help you that way.

Send us an e-mail

Tell us where you are, how many metres it is and what needs doing. A photo of the spot helps most.

info@stevigkitwerk.nl

We reply within 15 minutes on working days.

Choose how to get in touch

Chat with Kitty on WhatsApp